All is in place for the Sabina Park lighting project to be completed before the July 31 deadline.
Minister with responsibility for Sport, Natalie Neita Headley, along with Jamaica Cricket Association officials and a representative from the Indian High Commission assessed the progress of the project on thursday, where Project Manager Wayne Reid says the lights should be ready for testing by July 22.
Minister Neita Headley was satisfied with Reid’s update, and noted the equipment inclusive of the standby generators are all at Sabina Park awaiting final installation.
View the original article here
Sabina Park lighting on track for July 22 testing